Press Release - 2 February 2004
A Model of Change
Simulation Modelling, undertaken by Coventry-based
Production Modelling http://www.simulation.co.uk,
has played a key role in both the successful delivery, and the on-going
management, of an expanded warehouse and distribution facility for
Walkers Snacks Foods.
One organisation that is benefiting significantly
from the use of simulation technology is Walkers Snack Foods Ltd.
The company recently invested in a major expansion of its Leicester
based factory and warehousing complex, which includes its Southern
Region Distribution Centre (SRDC), and equipment and process simulation
played a crucial dual role in this project. As well as proving the
design concept, and providing detailed process analysis that led
to direct project savings, a detailed simulation model was also
developed that is now being used an operational management tool.
Walkers’ Leicester complex includes two factories with seven
production lines, and prior to the latest development there was
also a single warehouse, with storage for 9800 pallets, and the
SRDC, which provides case storage, picking facilities and marshalling
lanes. This warehouse and the SRDC are sited side-by-side, and directly
linked through a monorail system, that basically runs on a circular
track round the SRDC. The expansion project, which was designed
and implemented by warehouse solutions specialist Swisslog together
with Walkers’ project team, has seen the introduction of a
new warehouse on the other side of the distribution centre. However,
rather than just provide additional storage space for 13320 pallets,
the project’s aim has been to fully integrate the new warehouse
with the existing facilities through the monorail system, (essentially
feeding goods from the opposite side) and so create a combined operation
that can deliver a significant increase in peak throughput, from
200 to 320 pallets / hour.
As John Coates, project director for Walkers Snack Foods, explains,
“We believed that the existing facilities, and in particular
the monorail system, had latent distribution capacity that could
be utilised through this expansion project. But, significant questions
remained as to whether the monorail would simply become too easily
grid-locked in practice, when being fed from both sides, and what
changes would be needed in equipment and infrastructure to handle
more goods.”
To help confirm the concept and answer specific questions, the joint
project decision team comprising of Walkers, IMI and Swisslog staff,
turned to simulation technology and Coventry-based Production Modelling,
a specialist provider of simulation, planning and scheduling software
and consultancy.
“This simulation project has had two distinct phases,”
notes Tim Cooke, senior project consultant at Production Modelling.
“Initially we used our ProModel simulation software to model
specific aspects of the system, in particular the monorail system.”
This model was not only able to answer the key question, that the
system could be used as anticipated without any major configuration
changes, but also provided important data for the overall project
that would have only been found by expensive trial and error. For
a start, it had been anticipated that to meet the increase in demand,
up to six more monorail trolleys could be needed. But, the simulation
was able to prove that there were already enough trolleys on the
existing system to deliver the required increase in throughput,
which meant a direct project saving of up to £150 000. The
simulation further confirmed that when the system was not being
run at peak throughput, it would be possible to park the unused
trolleys in a new parking area, thus avoiding having to constantly
rotate empty trolleys together with full ones.
“The flow of products within this new combined facility is
very complex, and the simulation also highlighted how significantly
the spread of products through the two warehouses could affect throughput.
From this we were able to help assess and determine the best storage
and dispatch rules for delivering the required throughput,”
says Cooke.
The second phase of the simulation project was the development of
a far more detailed model of the whole combined operation, which
could be run at SKU level. However, as well as confirming the design,
and helping to determine optimal operational speeds and feeds for
various equipment, this model was developed for far more long-term
reasons.
“We intentionally decided to invest in a far more detailed
model than was strictly necessary for the design confirmation, because
we recognised the important role such a model could play as an everyday
management tool, helping with the ongoing management and development
of the operation and its staff,” reports Coates. He adds,
“It will prove invaluable for training front line managers,
and all the SRDC staff - getting them used to the system on the
model and learning about key issues. It is also currently being
used to assess existing operational practices, and this has already
shown that there is potential in the system for further improvements.”
Coates concludes, “Overall, the decision to apply simulation
technology, and the expertise of Production Modelling, has proved
to be a key aspect in the successful delivery of this project.”
End. |

|
Our Work
To see how we have helped companies see our Case
Studies
|